Alteration map to drill fence: setting spacing on a porphyry vector

Layered sedimentary rock outcrop rising from a scrub-covered slope under a clear blue sky.

You've got a wide-swath alteration map sitting on the GIS desktop and a drill budget that needs committing. The halo looks real: clay out at the margins, a carbonate rind further in, iron-oxide staining tracking what might be a leached cap. Now someone wants a fence spacing plan by Friday. That conversion follows a specific order, and it's worth walking through how a vectoring exercise usually runs it.

Reading the zonation before you touch a spacing number

Before any fence gets drawn, the alteration map needs to be read as zonation, not as a blob of color. A SWIR-derived layer that lumps "clay" into one class and "carbonate" into another is giving you mineral chemistry, not geometry, until you overlay it on topography and structure and ask which way the zones are telling you to look.

Argillic and phyllic signatures usually sit outboard of a porphyry center; propylitic carbonate sits further out still, often draped across a much bigger footprint than the ore shell itself. Iron-oxide staining from an oxidized leached cap can mislead you if you read it as proximal when it's sitting over supergene enrichment that's moved laterally off the primary source. None of that comes free from the raster. It comes from someone who's walked outcrop in the district overlaying the pixel classes against known lithology and structure, then asking where the zonation looks asymmetric, pinched, or offset, because that asymmetry is usually the thing worth drilling toward.

Get the vector direction wrong at this stage and the fence spacing plan downstream is just precise placement of the wrong holes.

Turning halo width into fence spacing

Once you've got a defensible vector, convert it to geometry. The rule of thumb most porphyry programs use is that fence spacing should be a fraction of the alteration halo's apparent width along strike, tight enough to catch the zonation change between fences, loose enough that you're not burning meters confirming what the last fence already told you.

A halo that reads 400 to 600 meters wide on the SWIR pass supports first-pass fences at something like 100 to 150 meter spacing across strike, with step-outs widening once the first couple of fences confirm the orientation. A narrower, sharper-edged halo, the kind you sometimes see where structure has telescoped the alteration against a fault, wants tighter fences and probably a reoriented azimuth, not the same spacing rotated to match the old assumption.

Fence spacing decisions also run through rig economics. RC fences for a first pass can run tighter and cheaper than diamond; once a fence hits the zonation you expected, the next decision is whether to infill on the same line or step the whole fence out along strike toward where the halo is still open. The alteration map doesn't make that call for you. It tells you where the halo is thickest and where it's pinching out, and a geologist decides whether thickest means center or means supergene thickening that's wandered off target.

What the remote-sensed pass actually buys you here

A tenement-wide pass gives you a first-pass alteration model across ground you haven't walked yet, so the fence spacing conversation starts from a defensible zonation model instead of from outcrop you happened to log on the access track. A fingerprinted clay, carbonate, and iron-oxide layer covering the whole campaign area, like the one built for exactly this hand-off, means the vectoring argument gets made before the first hole goes in rather than after three fences come back ambiguous.

If you're staring at a tenement with no field alteration model yet and a drilling campaign to vector, an alteration halo layer built from the wide-swath SWIR pass is the starting point worth putting in front of the budget committee before the rig mobilizes.